If you’re inside the 12-week window, immediate action is still valuable:
6-8 Weeks Before Holiday:
- Focus on highest-priority orders only
- Expedite material orders with premium freight if necessary
- Schedule immediate quality inspections
- Negotiate priority production slots (expect to pay premiums)
4-6 Weeks Before Holiday:
- Conduct rapid supplier capacity audit
- Identify which orders can realistically complete before shutdown
- Prepare contingency plans for post-holiday rush production
- Consider air freight for most critical items
Inside 4 Weeks:
- Accept that some delays are inevitable
- Focus damage control on most critical customers
- Prepare communication plans for delayed deliveries
- Document lessons learned for next year
Critical Lesson: Late planning costs 3-5x more than early planning. Start your 2027 preparation immediately after the 2026 holiday concludes.



Leave A Comment